YaHoo! Data Center
 
Just thought I would write something about the new YaHoo! Data Center Just outside Omaha, NE. I am a director of warehouse and distribution for a direct mail company. Because of the economy we decided to scale down the operation from a 400,000 sq ft building to around 100,000 sq ft. To our surprise we found out YaHoo! was looking for a location in the midwest for a large datacenter. To make a long story short they now own the 400,000 sq ft facility.

Watching the construction process is amazing to say the least. They started the process 4 months before we were even out of the facility. At this time they have only made 80,000 sq ft of the facility dust free and suitable for a server farm. Working very closly with the General Contractors I have made several visits over there since we moved out.

The floor of course is raised 4' from the concrete surface with 24" x 24" tiles covering over 7 miles of cooling fluid tubing and power lines. Have you ever seen a generator that is the size of a locomotive? They have six of them that produce enough electricty to power over 40,000 homes.

The cooling fluid tubing routes underground to the GIANT chillers located roughly 50 yards from the building. Along with the water chillers are 3 separate air handling units that will help regulate the air temprature during the 100 degree summer days and the -30 degree winter days. All of these units are just bigger than a locomotive.

Back to the server floor. I recently visited there and they were in the process of setting and anchoring the server rack frames. I was surprised to see that the server frames are not much taller than your typical server rack. Just wider and deeper for access. The server frames also house a very large radiator at the top to dicipate heat. The server racks, when installed, will be located on the outside of the rack frame with the actual server cooling fans facing the inside of the rack frame.

The cooling fluid tubing from under the raised access floor will be piped in 1" lines around the actual servers. Not sure how that will be done. The heat from the servers will warm the cool water and then vent that warm water thru the radiators and back to the chillers for recirculation. Hope that makes sense.

Anyway, I am going to be one of the very privlidged people at the ribbon cutting ceremony when it is completed. I will post pictures when that happens. I believe they want to be operational in Sept.

And I had to ask the question, how many server will be located in this 80,000 sq ft. My chin hit the floor when the GC said "oh, about 27,000 servers" :eek:

Anyways, I will post some pictures of the outside soon.


الساعة الآن 04:50 AM

Powered by vBulletin® Copyright ©2000 - 2026, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.5.2 TranZ By Almuhajir


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227